How do I create a project in Tasktrestle?
Learn what to enter for a Tasktrestle project, including task IDs, durations, planned dates, working days and dependencies.
How do I create a project in Tasktrestle?
For contractors and project managers building a schedule, start with Create project. Enter a project name, a project start date and at least one task.
What does each task need?
Give each task a distinct ID and a name. Then supply either:
- A duration in working days.
- A planned finish date.
If you supply both, they must agree. You can include up to 200 tasks in a project.
You can also add a trade or crew label, an earliest planned start, predecessor task IDs and a percent complete.
Do I need a start date for every task?
No. Task starts default to the project start. A task's scheduled start also accounts for its predecessors and the working calendar.
Use dates in YYYY-MM-DD format, between 2000 and 2099.
How do I set the calendar?
Choose the working days and add any holiday dates to skip. If you leave the calendar unchanged, Tasktrestle uses Monday through Friday with no holidays.
What do I get back?
Tasktrestle returns the project ID and the schedule, including each task's requested start, scheduled start, scheduled finish, duration, dependencies and progress.
Use Projects to find a saved project, then View project to review its full schedule.